Funding for the Wales Millennium Centre
02/10/2008
Welsh Assembly Government managed risks well during construction but not after opening, says Auditor General
  Jeremy Colman 
Audio files icon 

Interviews
Click here for an introduction by the Auditor General (click here for the transcript)
Click here for more information from James Verity (click here for the transcript)

 PDF icon Report - click here to download the report
Click here to view the press release
 PDF icon

Other documents
November 2005: Funding for the National Botanic Garden of Wales

 

During the construction of the Wales Millennium Centre (WMC), the Welsh Assembly Government did a good job overall in managing the risks it faced as a key funder. But, according to the Auditor General for Wales, it was not on top of the continuing risks once the WMC had opened. His report, published today, says the Welsh Assembly Government was not fully alert to the risks until the WMC reached a financial crisis and requested additional public funds. In all, the project cost just over £109 million (see notes to editors) and has required more public money than originally expected.

Click here for the full press release

<< Previous article Next article >>